Construction progress continues to advance, with significant progress recorded in façade installation and structural works.
One critical site condition has been identified in the south-east sector relating to standing water and drainage performance, requiring immediate attention.
Overall project progress is estimated at 72%, representing a 6% increase compared with the previous reporting period.
| REPORT ID | TITLE | TYPE | PERIOD | STATUS | GENERATED ON | RECIPIENTS | ACTIONS |
|---|---|---|---|---|---|---|---|
| R-021 | Weekly Progress Report | WEEKLY | 24 AUG – 31 AUG 2026 | ISSUED | 31 AUG 2026 11:00 GST | 3 recipients | |
| R-020 | Weekly Progress Report | WEEKLY | 17 AUG – 24 AUG 2026 | ISSUED | 24 AUG 2026 10:15 GST | 3 recipients | |
| R-019 | Monthly Progress Report | MONTHLY | AUG 2026 | ISSUED | 01 SEP 2026 08:00 GST | 5 recipients | |
| R-018 | Technical Report | TECHNICAL | Site Survey Analysis | ISSUED | 28 AUG 2026 16:40 GST | 2 recipients | |
| R-017 | Weekly Progress Report | WEEKLY | 10 AUG – 17 AUG 2026 | ISSUED | 17 AUG 2026 09:30 GST | 3 recipients | |
| R-016 | Findings Report — F-007 | FINDINGS | Standing Water | REVIEW | 16 AUG 2026 14:10 GST | 2 recipients | |
| R-015 | Monthly Progress Report | MONTHLY | JUL 2026 | ISSUED | 01 AUG 2026 08:00 GST | 5 recipients |